East Sunset Drive roadway widening
Contractor completed drilling all 17 pier holes on the downslope retaining wall and 26 pier holes on the upslope retaining wall. They installed steel I-beams and poured concrete to 11 pier holes along the downslope and 4 pier holes along the upslope. The project is scheduled to be complete in mid-July.
2022 Pavement Rehabilitation and Drainage Improvement Project
The construction contract for this project will be advertised on the Los Altos Crier on July 6 and July 13, 2022. Bid opening is July 27, 2022, at 2 PM. Staff will also notify the Builders Exchange and paving contractors of the upcoming bid.
EVSE Town Hall
Public Works is working on obtaining building permit, as well as meeting ADA requirements for whole scope. Once the permit is approved, we will be able to order EV chargers. Once design is approved public works will be able order EV chargers.
Prop 68 (Concession Stand at Purissima Park) contract awarded and scheduled
Contract awarded on May 25, building permit has been submitted and under review. Expect construction to start in September. Submitted request to PG&E to upgrade the electrical service panel, lead time for electrical panel is 120 days.
Matadero Creek Repairs
Continue conversation with water board (Brian Wines) an alternate of site mitigation plan was submitted on 5/19/22, initial comments from Brian indicate that the deed restrictions for the property would not meet the water board requirements as it does not guarantee that the plantings can’t be removed in the future, a possible solution would be to add specific deed restrictions to the mitigation area.
WestBay Contract
New five-year contract approved by City Council on May 25, the new contract starts on 1 July 1, 2022.
Corp Yard Site Improvements
Preliminary Design complete and topographic survey has been completed; this will be used to finalize the design. Once the design is complete the project will be submitted to planning for public hearing. The goal is to complete construction before the next rainy season (Mid October).
Annual Sanitary Sewer Replacement and Rehab CIP 2022
Staff determined 61 locations for repair, working on preparing the contract package including contract drawings and specs.
Pathways Projects
Robleda / La Paloma trail
Completed the first section of the trail, including retaining walls and bridge, planning to work on it couple days this week and expect completion by the end of June.
Concrete and lumber picked up on Monday for retaining wall and water bar work. Work beginning on the last retaining wall going up the hill from Robleda Rd begins Thursday June 9 and will continue through Saturday June 11. If retaining wall finished, we will begin to brush and clear top section to connect with La Paloma side of pathway.
Summer Hill Pathway
Town is currently soliciting design services from consulting firms to complete the final pathway design and prepare construction drawings. The bid proposals are due on 6/10/2022
Encroachment Permits Issued: 2
Private Pathways Projects
La Cresta Sewer Main Extension
Currently in the plan review process.
Camino Hermoso Sewer Main Extension
Currently in the plan review process.
Maintenance
After hours or weekend callouts: 2
Fallen trees/major limbs down: 0
Purissima Park
Repair irrigation, aerate and over seed fields. Investigated small leak, Concession Stand had a leaking faucet and repairs underway for broken water bottle filler. Part ordered to fix restroom.
Routine Maintenance
Repair broken lines and leaks at Town Hall near EV charging trenching. ROW mowing on Page Mill Rd. for fire prevention..