Public Works
Engineering
Page Mill Road Tree Survey
Consultant updated that report may take until end of August currently in discussion with consultant to receive an updated date.
CIP Projects
East Sunset Drive roadway wideningProject COMPLETE!
2022 Pavement Rehabilitation and Drainage Improvement ProjectStaff received five bids on July 27, 2022. Staff will bring the project to City Council and recommend awarding a contract to the responsible low bidder on August 18 regular meeting.
Town Hall AdditionWaiting for final Change order documentation to process final invoice and to close the project. This will be on the Council agenda in September to close the project.
Corp Yard Site ImprovementsStaff reached out to three contractors and received two bids. The low bidder was selected and notified. A recommendation to award the contract for this project will be on the agenda of the August 18 council meeting. Since the contract amount for this project is below $200,000 and the procurement process for a construction contract is based on the Town Bidding procedure
2-4.04 (section b-1) and Public Contract Code section
22032.
EVSE Town HallThe underground contractor will return on August 5 to complete the remaining work of the underground scope to provide for three additional charging stations.
Staff has issued a work order for an electrical contractor to redirect the power feed for the Parks & Rec building from the current PG&E overhead line to the Town Hall’s electrical room. After the cutover, the utility bill for the Parks & Rec building will be reduced by at least 53%.
Staff will present the “Resolution Approving the Designation of System Low Carbon Fuel Standard (LCFS) Credits to PowerFlex” at the council meeting in August.
Prop 68 contract award and scheduleContract awarded on May 25, Engineering has drafted a response to address individual comments provided in the second review and provided design changes as required.
Sewer root foaming 2022 Staff completed a comprehensive review of sewer maintenance reports for the past four years and identified 50,000 linear feet of sewer mains for root foaming this year. Root foaming will stun the growth of protruding roots at sewer joints and reduce the risk of sanitary sewer overflows. Root foaming will be performed in two stages. On 7/22/22, staff finalized and submitted a list of sewer mains, (23,729 LF) identified for root forming. Staff has identified additional 22,796 LF of sewer mains for root foaming. The list will be finalized and provided to West Bay within the next few weeks.
Purissima Lift StationAs of 7/28/22. both sewage pumps in the wet well at the Purissima Lift Station have been upgraded. The upgrade includes installing a brand-new pump and a rebuilt pump. The Town now owns three sewage pumps for the wet well. The third pump will be rebuilt and kept in the Corp Yard as a spare. In an event a sewage pump fails, the spare pump will be used to replace the failed pump and keep the lift station operational.
Pathway Projects
2022-23 Pathway ProjectsDeveloping of a comprehensive list is ongoing, the list will identify areas where the Town already has the Pathway easements, but no improvements have been made. This list will serve as the comprehensive Pathways CIP and the list will be prioritized to develop the plan for each year.
Summer Hill PathwayStaff have selected a designer for this project and will go to Council for approval in August.
Edgerton pathStaff has reviewed and approved a preliminary pathway alignment proposed by a consultant. Staff has also provided review comments to improve pathway design.
Fremont to Redwood Grove PathwayLos Altos and Los Altos Hills City Managers are discussing the path forward on this project.
Page Mill Road Crosswalk at Foothills ParkStaff has requested proposals to design an ADA compliant crosswalk to meet the city of Palo Alto requirements.
Maintenance
After hours or weekend callouts: 0
Fallen trees/major limbs down: 0
Routine Maintenance
- Hot Crack Fill for Annual resurfacing project in conjunction with the engineering department. Roughly 3.5 centerline miles completed this week
- Small limb down on Magdalena Rd and Stonebrook Rd.
- Replace damaged sign on Page Mill Rd.
- For Giants Baseball Camp at Purissima Park
- Equipment Maintenance
- Built new path posts
- Purissima Park: mowing, field dragging, arena dragging, and trash pickup.