Public Works
Storm Events/Sanitary Sewer Overflow
On January 31, Public Works staff responded to a sanitary sewer overflow (SSO) in Adobe Creek near Moody Road and Old Snakey Road attributed to storm events. The concrete cap surrounding the older sewer line in Adobe Creek was damaged due to erosions from the storms ultimately resulting in a pipe failure. On February 3, Town’s contractor mobilized on site and completed the replacement of the damaged sewer pipe by February 7. To prevent further erosion around the pipe and the concrete cap, subsequent work is required during the summer once water levels recede in Adobe Creek.
Grading Moratorium
The Grading Moratorium is in effect from October 1, 2022, to April 30, 2023. Construction inspections throughout the Town in effect throughout the Town for ongoing construction projects.
Pathway Projects
Saddle Court Pathway
Survey staking work started this week. Notices were sent to residents near work to be performed. With the staking, staff will be able to evaluate and plan out construction for Saddle Court Pathway in the summer.
Summerhill Pathway
Staff is anticipating to receive the final design plans from the design consultant by next week. Staff will then submit the design plans to the County for their approval and encroachment permit.
New Pathway Segments for 2023
As a result of the Council goal setting/work plan meeting on January 25, staff is coordinating with the Pathways Committee to identify approximately 3.6 miles of pathways to be constructed in 2023. At the March 16 City Council Meeting, staff is planning to present the timeline and resources needed to construction 3.6 miles of pathways this year for Council’s consideration.
Annual Road Rehabilitation CIP Project
An inspector for the Town will be out on Town streets starting February 10 to verify, quantify, and mark out work limits for this year’s Road Rehabilitation Project. Town staff will gather the field data and finalize the project Plans and Specifications for bid by April 2023.
Sewer CIP Projects
2022 Sanitary Sewer Repair and Replacement Project
The 2022 Sanitary Sewer Repair and Replacement bid package was posted on the Town’s website on Wednesday, February 1. “Notice to Bidders” will be advertised on the Los Altos Town Crier beginning on February 8 for two consecutive weeks. The bid opening is scheduled at 2:00 pm on March 2, 2023 at Town Hall.
Permits Issued
Encroachment Permits: 2
Sewer Permits Issued: 0
Maintenance
After hours or weekend callouts: 1
Fallen trees/major limbs down: 2
- Inspect and clean storm drain inlets throughout Town
- Replace multiple street signs throughout Town
- Maintain/repair infields at Purissima Park for start of Little League Season
- Fallen trees removed on Via Ventana Way and Summit Wood Rd.
- Install erosion control and cleanup work on Moody Rd.
- Mow, clean and blow Purissima Park