Public Works
Grading Moratorium Grading Moratorium in effect from Oct. 1, 2022, to April 30, 2023. Construction inspections throughout the Town in effect throughout the Town for ongoing construction projects.
CIP Projects Town Hall RenovationThe renovation project continues to be on schedule and will take three weeks to complete. The contractor mobilized onsite on November 10th and the anticipated completion date is still December 2.
2022 Sanitary Sewer Repair and Replacement Project
Staff has identified and evaluated 40 sanitary sewer segments with structural defects for consideration in the 2022 CIP. Of the 40 segments, staff has narrowed down the list to 17 segments. The tentative schedule for the 2022 CIP is to request the Council’s permission to advertise the project in December, advertise the project in January, open bids in February, award in March, and begin construction in April.
Adobe Creek Sanitary Sewer StudyThe survey crew from Freyer & Laureta (F&L) were onsite on November 17 to collect additional survey data of the existing sewer manholes on Moody Road and Rhus Ridge Road. F&L anticipates finalizing the sewer study report with the Rhus Ridge Road sewer bypass option three weeks following the topo survey. We will make the study public shortly thereafter.
Pathway ProjectsBriones Way PathwayTown sent notices to homeowners for construction of the Briones Way pathway. The project is scheduled to begin in late Winter, with completion in early Spring.
Saddle Court Pathway
Grant of Pathway (Trail) easement document is complete. The City Council adopted the two resolutions at the November 17, 2022 City Council meeting. 1) Vacating of existing Trail Easement; 2) Accepting new Pathway (Trail) easement.
Permits Issued:
Encroachment Permits: 0
Sewer Permits Issued: 0
Maintenance:
After hours or weekend callouts: 1
Fallen trees/major limbs down: 2
PW Maintenance Crew
- 0 after hour/weekend callouts this week
- 0 fallen trees/major limbs down for the week
- ROW blowing and storm drain cleaning throughout town
- Mowed Purissima Park
- Off haul spoils from storm drain cleaning
- Repair asphalt crack on La Loma RD
- SSO response on Dezahara Way