Page Mill Road Tree Survey – Consultant updated that report may take until end of August currently in discussion with consultant to receive an updated date.
CIP Projects
East Sunset Drive roadway widening – Project is complete as of 7/27/2022. The contractor will clean up staging area at Purissima and Elena Roads.
Matadero Creek - No update.
2022 Pavement Rehabilitation and Drainage Improvement Project -Staff received five bids on July 27, 2022. Staff will bring the project to City Council and recommend awarding a contract to the responsible low bidder on August 18 regular meeting.
Town Hall Addition – This will be on the Council agenda in September to close the project.
Corp Yard Site Improvements: Contract drawings have been finalized, and staff has reached out to several contractors to solicit bids. Since the contract amount for this project is below $200,000 and the procurement process for a construction contract is based on the Town Bidding procedure 2-4.04 (section b-1) and Public Contract Code section 22032.
A Site Development public hearing for this project was conducted on July 19 with the planning committee. This improvement project did not receive any protest from public and was approved for construction.
Staff will bring recommendation for contract award during the August council meeting.
EVSE Town Hall – The Electrical contractor has made the cut-over for the existing ChargePoint charging station in the Town Hall parking lot on 7/8/22, and increased charging capacity by 100% with two separate 40-amp circuits. The charging station now draws power from the electrical room in the Town Hall and relies on renewable energy generated by the Town’s solar panels on the rooftop and in the Native Garden.
The underground contractor will return onsite in the first week of August to complete the remaining scope, including constructing two additional concrete foundations and installing remaining conduits. This will allow for installing three additional charging stations and increasing capacity from two charging ports to six charging ports.
Staff also plans to redirect the power feed for the Park & Rec building from the current PG&E overhead line to the Town Hall’s electrical room. This will further reduce the Town’s overall energy bills as the unit electricity rate for the Town Hall is half of that for the Park & Rec building. In addition, this will also increase the consumption of and reduce back feeding excess solar energy generated by the Town’s solar facilities.
Staff will present the “Resolution Approving the Designation of System Low Carbon Fuel Standard (LCFS) Credits to PowerFlex” at the council meeting in August.
Prop 68 Concession Stand contract award and schedule – Contract awarded on May 25, Engineering has drafted a response to address individual comments provided in the second review, and provided design changes as required.
Sewer CIP 2022 – No update
Sewer root foaming 2022 – Staff completed a comprehensive review of sewer maintenance reports for the past four years and identified 51,000 linear feet of sewer mains for root foaming this year. Roof foaming will stun the growth of protruding roots at sewer joints and reduce the risk of sanitary sewer overflows. Root foaming will be performed in two stages. Root foaming will be performed on 25,000 linear feet of sewer mains in Stage 1, and the remaining will be done in Stage 2.
Purissima Lift Station – The second of the two sewage pumps in the wet well at the Purissima Lift Station installed by our vendor, Shape Inc., on 7/28/22. The first sewage pump, a new pump, was installed in the wet well on 4/19/22. By installing a new sewage pump and a rebuilt sewage pump in the wet well, this completes the routine maintenance service of sewage pumps and reduce the risk of pump failures at the lift station.
Pathway Projects
2022-23 Pathway Projects – Staff started work on the new approved pathway projects for 2022-23.
Summerhill Pathway- Staff have selected a designer for this project and will seek Council approval in August.
Edgerton path – Staff has reviewed and approved a preliminary pathway alignment proposed by a consultant. Staff has also provided review comments to improve pathway design.
Fremont to Redwood Grove Pathway – Leadership teams from the City of Los Altos and Town of Los Altos Hills are discussing the "path" forward on this project.
Page Mill Road Crosswalk at Foothills Park – Staff has requested proposals to design an ADA compliant crosswalk to meet the city of Palo Alto requirements.
Encroachment Permits Issued: 4
Sewer Permits Issued: 1
Maintenance
After hours or weekend callouts: 1
Fallen trees/major limbs down: 1
Routine Maintenance
- Hot Crack Fill for Annual resurfacing project in conjunction with the engineering department - Roughly 4 centerline miles completed this week
- Small limb down on pathway behind Central Ave path
- Replace downed sign at Purissima Park
- Limb trimming visibility trimming on Magdalena and Ravensbury near ALPR and corner
- Friday, trash pickup at Purissima Park, weed abatement and clean up at Purissima Park in preparation for Giants Baseball Camp
- Purissima Park: mowing, field dragging, arena dragging, and trash pickup.