Public Works
"Thank you for repaving West Loyola Drive...It is absolutely fabulous." Resident, Kerry Hallow
CIP Projects
Matadero Creek Erosion
Staff is working with the consultant to prepare a deed restriction on two vacant properties owned by the Town as required by the permit application
2022 Pavement Rehabilitation and Drainage Improvement Project
COMPLETE
Town Hall Renovation
The construction schedule for the Town Hall interior renovation has been finalized to start on 11/10, and complete on 12/9. Customers will be serviced from the Council chambers until our the space in Town Hall is complete.
Prop 68 Concession Stand Building at Purissima Park
This project will begin on Monday, October 24. The contractor will mobilize onsite and set up a temporary construction fence around the work area. The construction fence will remain in place for two months.
Heritage House Improvements
The contractor is onsite on Thursday to make the final conduit connection between the pull box and the buildings. The complete conduit run will allow the contractor to pull a CAT6 ethernet cable and terminate the cable on both ends. The homerun CAT 6 ethernet cable from the IT room will provide high-speed internet connectivity and IP phone service in the Heritage House. The EPRC and History Committee will be consultant before final plans are approved. The ultimate goal is to make the building more usable by the committees and the public for meetings and gatherings while preserving the historic character and elements related to ham radio communication.
Town Hall Parking Lot CCTV Camera
In an effort to make our parking lot more secure we are installing security cameras. The contractor is onsite on Thursday and Friday10/20 - 10/21 to install 30 ft of 1-inch conduits in the Town Hall parking lot and construct a new concrete pole base. This infrastructure will be used to install a hard-wired CCTV camera system.
Pathway Projects
Briones Way Pathway
Town sent notices to homeowners for construction of Briones Way. Pathway construction to begin between late October and mid-November.
Edgerton path
Staff has value engineered the pathway design to reduce the length of retaining walls and the number of wood posts. Staff has also modified the pathway profile elevations to minimize excavation spoil off-haul. The revised design should reduce construction cost to below $200K and shorten the construction duration. This project will require additional funding than what is allocated in the CIP budget. Expect to see an RFP for council approval for this project in the new year.
La Paloma Road Pathway
Town sent notices to homeowners for construction of La Paloma Rd. Pathway, beginning between late October and mid-November.
Maple Leaf Court to Middle Fork Lane
Town awarded a contract to Giuliani & Kull, Inc. to stake the pathway easement boundary. The work is schedule between Monday, 10/31 and Friday, 11/4.
Page Mill Road Crosswalk at Foothills Park
Staff has received topographic survey points of Page Mill Road from the surveyor. This will allow the staff to design a pathway across Page Mill Road with ADA compliant ramps.
Saddle Court Pathway
Town staff began creating Saddle Court Pathway documents.
Summerhill pathway
Staff is looking to contact surveyors to gather additional topography survey data for the beginning of the pathway and to survey additional trees. Staff receiving bids from surveyors.
Grading Moratorium
Grading Moratorium in effect from Oct. 1, 2022 to April 30, 2023. Construction inspections throughout the Town in effect throughout the Town for ongoing construction projects.
Permits Issued:
Encroachment Permits: 3
Sewer Permits Issued: 0
Maintenance:
After hours or weekend callouts: 0
Fallen trees/major limbs down: 0
PW Maintenance Crew
- Unload and place final blocks for new Corp Yard material area
- Small tool equipment maintenance
- Painted red, blue and yellow curbs at Town Hall
- Removal of old and installation of new reflectors along guardrail on W Fremont Rd, Chapin Rd, and Page Mill Rd
- Mow turf at Purissima Park